Project Flow

Step 1

Agreement signed

Parties sign the Lease Agreement. Customer provides performance bond / deposit within 14 days.

Step 2

Design and permits

Designing the System and helping with permits. Customer provides documents, information and site access needed for permits.

Step 3

Installation

Installing the System on the Customer's roof and connecting it to the Farm's electrical system. Customer supports access, safety, and power shutdowns when needed.

Step 4

Testing and COD

Lessor tests the System. When the System is ready and can run safely, Parties sign COD documents. The lease term starts on COD.

Step 5

Operation and Maintenance

System produces power each day. Customer uses the solar power for the Farm. Lessor monitors performance (24/7), cleans and repairs the System.

Step 6

Billing

Lessor reads the meter and calculates energy produced. Lessor issues invoices twice per month. Customer pays invoices within 10 days.

Step 7

Changes or Farm sale (if any)

If customer wants to move the System on the roof or to a new site, or sells the Farm, Customer must discuss with Lessor and follow relocation / sale rules in clause 13.

Step 8

End of term

At the end of the lease term, one of three things happens:
- Customer extends the term (if option exercised); or
- Customer pays the Early Termination Amount and buys the System; or
- Lessor removes the System from the roof and takes it away.